|
HIMACHAL PRADESH STATE ELECTRICITY BOARD
Download Complete 'Himachal Pradesh Clean Energy
Development Investment Program' in MS Word (Zipped)
Click Here
SUMMARY RESETTLEMENT PLAN (Draft)SAWRA KUDDU SUB PROJECT
SUMMARY RESETTLEMENT PLAN
A. Overview and Project Description
i. The Program,
Himachal Pradesh Clean Energy Development Investment Program (HCEDIP)
will be provided under a multi-tranche financing facility
lending approach over a span of 5 years which will facilitate
clean power generation, transmission, distribution, and sector
reforms in HP with minimum adverse environmental and social
impacts. This resettlement plan is prepared for the Sawra
Kuddu sub project which is based on the detailed engineering
design. According to the engineering design, it is assessed
that there will be significant impact on land acquisition and
resettlement and therefore a full Resettlement Plan (RP) is
prepared for the Sawara kuddu sub project. Sawra Kuddu Hydro
Electric sub project has been contemplated as a
run-off-the-river schenme on Pabbar river in Shimla district
of Himachal Pradesh.
ii. The RP contains
the extent of impact caused by land acquisition due to
construction of the sub project and spells out the
compensation and rehabilitation of the Affected Households (AHs)
and Affected Persons (APs). The RP is based on the detailed
engineering design and has been prepared in due consultation
with the stake holders especially the local people. Attempts
have been made by the engineering team during the design stage
to minimize land acquisition and resettlement by adopting
mitigate measures, i.e., selection of adequate site having no
settlement or land belonging to government which is free from
any use. However, there will be land acquisition required for
the sub project.
B.
Impact on Land Acquisition and Resettlement
iii. There will be a
total of 45.75 hectares of private land required for
acquisition for Sawra Kuddu sub project. The executing Agency
(EA) has already started the land acquisition process.
Approximately 32 hectares of land has already been acquired
and the compensation for land to the affected people has
already been disbursed. The assessment of land and
identification of affected persons for the remaining 12
hectares of land is in process for which section 4 and other
relevant sections of the Land Acquisition Act, 1894 (LAA) have
been initiated. The compensation amount for the remaining land
has also been fixed by the EA through its designated Land
Acquisition Officer (LAO) and the disbursement of money for
the remaining land is due. The compensation is based on the
market rate which is at replacement value. All the relevant
departments like revenue and PWD etc are involved in fixing
the replacement value of the losses. Therefore, the land
acquisition process is in smooth progress.
iv. The total private
land required for acquisition is 45.75 hectares which will be
required for various components of the sub project activities
such as construction of approach road, barrage site, tunneling
and construction of staff colony etc. There will be 2
residential structures which will be affected .The total
number of affected households due to the land acquisition is
165. A census survey was conducted to assess various impacts
of the affected households. A sample socio-economic survey was
also conducted to assess the socio-economic status of the APs
and the project influence zone. There will be no adverse
impact on indigenous people and on women. Summary of the land
acquisition and resettlement impact is presented in Table 1
Table 1: Summary Impact
|
Sl. No. |
Impacts |
Number/Amount |
|
1 |
Total area of agricultural land (hectare) |
45.75 |
|
2 |
Total number of households losing
agricultural land |
163 |
|
3 |
Total number of surveyed households |
100 |
|
4 |
Total number of structures (Residential)
affected |
2 |
|
5 |
Total number of community property resources
affected |
0 |
|
6 |
Total number of households affected |
165 |
|
7 |
Total Number of Vulnerable Households |
14 |
|
8 |
Total Number of tenants, Lease Holders and
Share croppers |
48 |
|
9 |
Total number of Trees |
1250 |
|
9 |
Total number of Titleholders |
165 |
|
10 |
Total number of non-title holders |
0 |
|
11 |
Total Number of Affected Persons (Aps) |
731 |
 
Download Complete
'Himachal Pradesh Clean Energy Development
Investment Program'
in
MS Word (Zipped)
Click Here
|